HomeMy WebLinkAboutOrdinance 0660ORDINANCE N0. 660
BE IT ORDAINED by the City Council of the City of ;lorth Richland
Hills, Texas, that ORDINANCE N0. 3$l, "Rules, Regulations, Policies and
Procedures for the City of North Richland Hills 4later and Sewer System"
adopted November 8, 171, arnended by ORDINANCE N0. 560, September 23, 1974,
and as heretofore amended be and the same is hereby amended to read:
SECTION IV, A. 3.
At locations where only a partial connection has been
previously paid for or installed, including only the
tap, service line or curb stop and setter, the applicant
for service shall pay (in addition to the meter deposit)
the cost of completing the Service Connection with meter
and box, which costs are non refundable.
For all services 3!4" through 6", an estimate of the cost
plus $50.00 for the connection will be provided by the City
and a deposit of the estimated amount will be required
before work is started on the installation of such connection.
Should the final cost of the work exceed the amount of the
deposit, a statement showing the amount of the excess will
be immediately furnished to the person having made the
deposit, and this amount will be due before water service
is actually begun. Should the final cost be less than the
amount of the estimate or deposit, a refund of over pay-
ment will be immediately made to the person from whom the
deposit was received.
SECTION IV, A. 4.
At locations where no part of the Service Connection is
existing, or previously paid for, but a Distribution Main
is existing adjacent to the property to be served, the non-
refundable Connection Charge plus $50.00 shall be quoted
by the City at the time of installation.
This is in addition to the meter deposit. Should the
Service Line required be longer than 50 feet, or should
the customer desire larger service, an estimate of the
cost for the connection will be provided by the City, and
a deposit of the estimated amount will be required before
work is started on the installation of such connection.
Should the final cost of the work exceed the amount of
the the deposit, a statement showing the amount of the
excess will be immediately furnished to the person having
made the deposit, and this amount will be due before
water service is actually begun. Should the final cost
be less than the amount of the estimate or deposit, a
refund of overpayment will be immediately made to the
person from whom the deposit was received.
Where applicable there shall be added the cost of street
repairs as follows: A minimum street cut of $100.00 shall
be deposited at the time water service is requested and
before service is started on on installation of such connec-
tion. Should the final cost of the work exceed the amount
of the deposit, a statement showing the amount of the excess
will be immediately furnished to the person having made the
deposit, and this amount will be due before water service
is actually begun. Should the final cost be less than the
amount of the deposit or estimate, a refund of overpayment
will be immediately made to the person from whom the deposit
was received.
SECTION IV, B. 2.
Where the furnishing of sewer service by the City does not
require the extension of Lateral Sewers or other sewer Mains
as defined under Point of Service to serve a new single customer,
the charge for the right to connect to the system shall be
Three Hundred, Five Dollars ($305.00). Except in a developed
subdivision where a developer has paid for the installation
of sewer facilities then the charge shall be Fifty Dollars
($50.00).
Where applicable there shall be added the cost of street
repairs as follows: A minimum street cut of $100.00 shall
be deposited at the time water service is requested and before
service is started on installation of such connection. Should
the final cost of the work exceed the amount of the deposit,
a statement showing the amount of the excess will be immedi-
ately furnished to the person having made the deposit, and this
amount will be due before water service is actually begun.
Should the final cost be less than the amount of the deposit
or estimate, a refund of overpayment will be immediately
made to the person from whom the deposit was received.
Each single customer shall be responsible for paying the cost
of tapping the sewer main or lateral. The City shall be
responsible for accomplishing the tapping of the Sewer Main or
Lateral and the installation of the required tapping saddle
and service sewer. Such work shall not be performed until the
City has received payment in full for this connection charge.
Passed and Approved this 11th day of April, 1977.
Tom E. Newman M~or
y
ATTEST:
'1
Je~nette Moore,
City Secretary
APPROVED FORM AND LEGALITY:
R.ex McEntire, City Attorney