HomeMy WebLinkAboutCIP 2026-08-10 Agendas t4RH
CITY OF NORTH RICHLAND HILLS
CAPITAL IMPROVEMENT PROJECTS (CIP) COMMITTEE AGENDA
4301 CITY POINT DRIVE
NORTH RICHLAND HILLS, TX 76180
MONDAY, AUGUST 10, 2026
REGULAR MEETING: 4:00 PM
A. CALL TO ORDER
B. PUBLIC COMMENTS
C. ACTION ITEMS
C.1 Selection of Chairperson
C.2 Approve minutes of the February 10, 2025 Capital Improvement Projects
Committee meeting.
C.3 Discuss and consider the 2026 Preventive Street Maintenance
Program.
D. ADJOURNMENT
Monday, August 10, 2026 Capital Improvement Projects (CIP) Committee Agenda
Page 1 of 2
Certification
I do hereby certify that the above notice of meeting of the North Richland Hills
Capital Improvement Projects (CIP) Committee was posted at City Hall, City of
North Richland Hills, Texas in compliance with Chapter 551, Texas
Government Code on Tuesday, August 4, 2026 by 5:00 PM.
Alicia Richardson
City Secretary/Chief Governance Officer
This facility is wheelchair accessible and accessible parking spaces
are available. Requests for accommodations or interpretive services
must be made 48 hours prior to this meeting. Please contact the City
Secretary's office at 817-427-6060 for further information.
Monday, August 10, 2026 Capital Improvement Projects (CIP) Committee Agenda
Page 2 of 2
"wFtH
O&TH KICHLA D HILLS
CIP COMMITTEE MEMORANDUM
FROM: Public Works Department DATE: August 10, 2026
SUBJECT: Selection of chairperson
PRESENTER: Kenneth Garvin, Public Works Operations Manager
SUMMARY:
The Capital Improvement Projects (CIP) Committee is comprised of three members and
one alternate. The committee selects a member to serve as chairperson to facilitate
meetings.
GENERAL DESCRIPTION:
The City Council, at its June 22, 2026 meeting, appointed the following elected officials
to serve on the Capital Improvement Projects Committee.
Name Place Term
Danny Roberts Member June 30, 2028
Matt Blake Member June 30, 2028
Kelvin Deupree Member June 30, 2028
Jack McCarty Alternate June 30, 2028
This is the first meeting for the new committee members, and the chairperson must be
selected from the membership.
RECOMMENDATION:
To select a member to serve as chairperson.
Ft
hJOKTH KIC:HLAND HILLS
CIP COMMITTEE MEMORANDUM
FROM: Public Works Department DATE: August 10, 2026
SUBJECT: Approve minutes of the February 10, 2025 Capital Improvement
Projects Committee meeting.
PRESENTER: Kenneth Garvin, Public Works Operations Manager
GENERAL DESCRIPTION:
The minutes for the previous meeting are placed on the agenda for review and approval
by the Committee. Upon approval of the minutes, an electronic copy will be uploaded to
the City's website.
RECOMMENDATION:
Approve minutes of the February 10, 2025 Capital Improvement Projects Committee
meeting.
MINUTES OF THE
CAPITAL IMPROVEMENT PROJECTS COMMITTEE MEETING
HELD IN THE COMMUNITY ROOM OF CITY HALL LOCATED AT 4301 CITY POINT
DRIVE
February 10, 2025
The Capital Improvement Projects Committee meeting of the City of North Richland
Hills met on the loth day of February at 4:00 p.m. in the Community Room.
Present: Suzy Compton, Council Member, Place 3
Kelvin Deupree, Mayor Pro-Tem, Place 7
Russ Mitchell, Council Member, Place 6
Jack McCarty, Mayor, Alternate
Staff Present: Paulette Hartman, City Manager
Caroline Waggoner, Assistant City Manager
Trudy Lewis, Assistant City Manager
Chase Fosse, Director of Budget and Research
Jay Patel, Director of Finance
Mary Peters, Director of Communications
Boe Blankenship, Director of Public Works
Kenneth Garvin, Public Works Operations Manager
Nathan Frohman, City Engineer
Harrison Fuller, Engineer Associate
Ariella Alfaro, Capital Project Manager
Dena Pierson, Office Coordinator
Craig Hulse, Director of Economic Development
Chris Amarante, Director of Facilities & Construction Manager
A. CALL TO ORDER:
Boe Blankenship called the meeting to order at 4:00 p.m.
B. PUBLIC COMMENTS:
There were no requests to speak from the public.
ACTION ITEMS
CA SELECTION OF CHAIRPERSON
Council member Compton nominated Kelvin Deupree as chairperson.
Council member Mitchell seconded the motion.
Motion to approve carried 3-0
C.2 APPROVE THE MINUTES OF THE APRIL 10, 2023 CAPITAL IMPROVEMENT
PROJECTS COMMITTEE MEETING.
Motion was made by Council Member Compton, seconded by Council Member
Mitchell.
Motion to approve carried 3-0.
C.3 DISCUSS AND CONSIDER THE 2025 PREVENTIVE STREET
MAINTENANCE PROGRAM.
Boe Blankenship thanked the chair and committee and gave a slide presentation
and answered questions about the presentation.
Boe Blankenship recapped the 2023 preventative maintenance program. There was
a budget of $2.7 million that was allocated to 17.4 center line miles on 128 streets.
All these projects are completed or very near completion with $409,000 savings.
He recapped the 2020 Bond Program. This was nearly $50 million bond with 28
projects to be done in phased construction taking 5-7 years to complete. 10 major
projects including full design, engineering and reconstruction are underway but are
not yet completed. 18 residential street projects were done in 3 phases, and we are
on the final phase and close to completion on all 18 streets.
We utilize 6 rehabilitation techniques. 1. 2" asphalt overlay — concrete curb and
gutter reconstruction as needed, wedge and joint milled, and then overlay 2 inches
of asphalt. 2. Asphalt rehabilitation — concrete curb and gutter reconstruction as
needed, remove all asphalt, add sub-grade stabilizers, and then 6 inches of asphalt.
We historically have partnered with Tarrant County Precinct 3 through an interlocal
agreement and plan to do so again this year. 3. Crack seal — routed and sealed to
prevent moisture in the cracks. 4. Slurry seal — seals fine cracks with a thin layer of
asphalt and aggregate and extends the pavement life. 5. Micro surfacing — seals
fine cracks with larger aggregate used on larger collector streets. 6. Concrete
patches. The streets were graded on the paving conditions from failed to good. The
cost difference between crack seal, slurry seal and rehabilitation is significant ($173
per linear foot). This program concentrates on the roads in the poor category.
Preventative maintenance keeps the number of streets needing rehabilitation from
growing.
No streets were repaired under the preventative maintenance program in 2024 due
to assessing streets for the next projects.
The recommendation for 2025 is to use the $409,000 savings, the 2024 $2 million
budget, and the 2025 $4 million budget for a total of $6.4 million to do maintenance
on 11.31 center line miles on 78 streets.
Chair Deupree asked if there were any other questions. There were none.
Motion was made by Mayor McCarty to accept the preventative street maintenance
program as presented and a seconded by Council Member Compton.
Motion to approve carried 4-0.
D. ADJOURNMENT
Chair Deupree adjourned the meeting at 4.34 p.m.
Kelvin Deupree, Chairperson
k4Ft
hJOIF LH KICHLAND HILLS
CIP COMMITTEE MEMORANDUM
FROM: Public Works Department DATE: August 10, 2026
SUBJECT: Discuss and consider the 2026 Preventive Street Maintenance
Program.
PRESENTER: Kenneth Garvin, Public Works Operations Manager
SUMMARY:
The Public Works Department has developed a recommendation for the 2026 Preventive
Street Maintenance Program. The proposed program is based on the recommendations
of the 2024 Pavement Assessment Project presented to City Council in May of 2024.
GENERAL DESCRIPTION:
The Preventive Street Maintenance Program serves as a strategic investment in the City's
roadway network, applying timely maintenance treatments that extend pavement life and
help reduce long-term rehabilitation costs.
Prior to 2018, project selection relied primarily on visual inspections conducted by staff.
Beginning with the 2019/2020 program cycle, the City adopted a more data-driven
methodology through the use of an external consultant equipped with advanced
pavement-assessment technologies to evaluate subsurface conditions and identify
potential structural concerns. This analytical framework supports both the current
program and a long-term strategy designed to maximize the value of public maintenance
dollars while enhancing pavement conditions community-wide.
Program Budget and Strategy:
This year's total program budget incorporates project savings carried over from a previous
project as well as newly allocated funds for a total program budget of $4,121,745. The
table below illustrates how the program budget was developed.
NRH Project # Funding Amount
SM2501 $121 ,745
SM2601 $4,000,000
Total $4,121 ,745
k4Ft
hJOIF LH KICHLAND HILLS
The proposed program places significant emphasis on asphalt overlays and asphalt
rehabilitation techniques to achieve broader system impacts. To accomplish the nearly 7-
mile project and streamline project delivery the Public Works Department has established
a process that will utilize multiple contractors operating under current agreements to
ensure efficient delivery, including the use of a turnkey paving contractor to consolidate
milling and paving operations. This approach is intended to shorten project timelines,
reduce service disruptions, and limit inconvenience for residents and motorists.
Major Projects and Partnerships:
One of this year's proposed street segments is Holiday Lane from the railroad tracks north
to Chapman Road where the city will utilize a longstanding interlocal partnership with
Tarrant County Precinct 3. This collaboration, which has been in place since 2011, has
consistently produced a cost-effective roadway rehabilitation solution where roads require
a more extensive process than a simple mill and overlay. Most recently, the Bursey Road
project from Hunter Lane to Bursey Road South was completed as part of this partnership.
Staff will deliver a concise presentation on this year's Preventive Street Maintenance
Program at the CIP Committee Meeting and will be available to address any questions.
RECOMMENDATION:
Recommend approval of the 2026 Preventive Street Maintenance Program to the City
Council.
2026
Overlay
Streets
Legend > a
Tj1-Surrey Ct 25-Live.Oak Or
2-Rio De Janeiro 26-Payte Ln
3-Willowcrest Ct N 27-Leaning Oak Or
4-Prank B St 28-North Oaks Or „.„, r� .„.� 1." ..
14�
5-Micke St 29-Wanda Way ...:: ...u..,.....V.Y _,... V,,.,� �. .�.....-_
6-Kendra In 3Q-Lowery Ln
-7 Johnson Ct TJ
�^31 Payte Ln
�.
B Jamaiica Cir -32-Greenwood Way a5.. „„ w. '..- ...,.,
9-Meadow Lakes Ct 33-Janetta Dr 1�` 'k 2a t.. I r...... ..:"'.'.
10-Carolenna Ct 34-Odell St 8 '
22.,..ry8 .., ..,.y
11-Tirnbeirhill Ct 35-Abby Rd .: 1 11 q mm
12-Tamiaml Ct 36-Janetta Dr
as qq
13-Wiindhaven Ct �37-Rolling Hills Dr {{ JI. f z
�.. .... 1
-14-Hunter Ln �-36-Post Oak Dr i 3 -
k, .
15-Victoria Ave 39-Weeping Willow Dr 36 ,p ..31 "36 .�%,,, L'"` 29
od
18-Cranrel Rd
,42g-Cumlings Drier f ...".�.� �'.... V16�...26 �3, .,,33
Ln ry� T
34� u..... Mµ,,.. 251,.
20-Green wood Dr 43-Noneman St ... .....
-19-In ...,."
21-Nonemaen St t �w�w�ww 4 Green Leaf Or ,�,, "�� '+ 26 0
Holiday d �,
37 9
®22-Parkwood Or 46,-Kris St .._ µ•-- m... Ell_
� ,1 .... -.k. ,..�,� ... ,,...
23-Lonesome Oak Or 47-Waterford Ct 1 ...,,,. ." .. m II
24-North Park Or
a �..rv ....
r µm as .. .. 9 1..4.a...
Mill&Overlay p�
Tarrant County
Rehabilitation - P 7
If Savings Allows Mill& fT
�wwwwwww Overlay � i �� &�� �•^t �I�.
17
32
.., ............ t.16 ,...m,m,m m ." .,.. ...�.y � gnMtl4WUN0.nfi" ✓
f' „ 0 0.5 1 2 Miles
ASPHALT OVERLAY
2O26 PREVENTIVE STREET MAINTENANCE PROGRAM
SURREY COURT
01 W2 6.8 MW $18,675.00 $30,024.00 $ 48,699.00
MEADOW LAKES DRIVE-CUL-DE-SAC
HEWITT STREET-DEAD END
SMITHFIELD ROAD-DEAD END
KIM LANE-CONTINENTAL TRAIL
PRICE DRIVE-CUL-DE-SAC
BOULDER ROAD-CUL-DE-SAC
TURNER DRIVE-CUL-DE-SAC
KIM LANE-CONTINENTAL TRAIL
RIVERVIEW DRIVE-LARIAT TRAIL
POST OAK DRIVE-BRIARDALE DRIVE
AMUNDSON DRIVE-MEANDERING DRIVE
POST OAK DRIVE-BRIARDALE DRIVE
AMUNDSON DRIVE-MEANDERING DRIVE
AMUNDSON DRIVE-MEANDERING DRIVE
Asphalt Overlay
Im2
28 42.9 NORTH OAKS DRIVE 295 $13,275.00 $19,498.00 $ 32,773.00
ROLLING HILLS DRIVE-CUL-DE-SAC
29 42.3 WANDA WAY 435 $19,575.00 $14,236.00 $ 33,811.00
WEEPING WILLOW DRIVE-MEANDERING DRI
30 42.6 LOWERY LANE 540 $24,300.00 $34,152.00 $ 58,452.00
NONEMAN STREET-DEAD END
31 42.6 PAYTE LANE 530 $23,850.00 $21,432.00 $ 45,282.00
NONEMAN STREET-DEAD END
32 15.1 GREENWOOD WAY 1,500 $67,500.00 $91,816.00 $ 159,316.00
LOLA DRIVE-MARY DRIVE
33 25.9 JANETTA DRIVE 1,165 $52,425.00 $90,904.00 $ 143,329.00
HOLIDAY LANE-CUL-DE-SAC
34 22.2 ODELL STREET 875 $53,958.00 $70,876.00 $ 124,834.00
TRADONNA LANE-CRYSTAL LANE
35 28.1 ABBY ROAD 660 $29,700.00 $43,256.00 $ 72,956.00
MAPLEWOOD AVENUE-JANETTA DRIVE
36 28.1 JANETTA DRIVE 840 $37,800.00 $61,278.00 $ 99,078.00
GENTLING PLACE-CLOYCE COURT
37 42.9 ROLLING HILLS DRIVE 815 $36,675.00 $24,232.00 $ 60,907,00
SOUTH CREST DRIVE-NOB HILL DRIVE
38 42.0 POST OAK DRIVE 1,560 $70,200.00 $103,454.00 $ 173,654.00
STARNES ROAD-HIGHTOWER DRIVE
39 42.3 WEEPING WILLOW DRIVE 770 $34,650.00 $34,740.00 $ 69,390.00
MEANDERING DRIVE-PRECINCT LINE ROAD
40 41.8 MEADOWVIEW TERRACE 1,460 $65,700.00 $99,657.00 $ 165,357.00
STARNES ROAD-GREENLEAF DRIVE
41 28.2 CRYSTAL LANE 665 $29,925.00 $47,234.00 $ 77,159.00
CRYSTAL LANE-CUL-DE-SAC
42 40.5 CUMMINGS DRIVE 2,545 $114,525.00 $183,350.00 $ 297,875.00
TURNER TERRACE-RIVIERA DRIVE
43 39.8 NONEMAN STREET 1,145 $51,525.00 $93,154.00 $ 144,679.00
SMITHFIELD ROAD-LOWERY LANE
44 46.0 HOLIDAY LANE 2,290 $407,546.00 $84,384.00 $ 491,930.00
R?R TRACKS CHAPMAN ROAD
TOTALS $1,820,054.00 $2,158,478.00 $3,978,532.00
SM2501-$121,745 $4,121,745.00 $3,978,532.00
SM2601-$4,000,000
46.0 GREENLEAF DRIVE 1,625 $73,125.00 $135,300.00 $ 208,425.00
CROSSTIMBERS LANE DOUGLAS LANE
41,1 KRIS STREET 1,050 $47,250.00 $128,492.00 $ 175,742.00
ONYX DR.N.-JERRELL STREET
ULSTER DR-CUL-DE-SAC _T 150 $6,750.00 $16,758.00 $ 23,508.00]4.0 WATERFORD COURT
***-IF FUNDING ALLOWS
Asphalt Overlay
2 of 2