RESOLUTION NO. 92-36
WHEREAS, the City of North Richland Hills will be improving the Calloway Branch
channel between Maplewood Avenue and Lola Drive and;
WHEREAS, Mobil Pipe Line Company (Mobil) will have to adjust an 8-inch and 16-
inch pipeline to avoid conflict with this proposed concrete channel liner project, and;
WHEREAS, Mobil will require 100% reimbursement from the City for all costs
associated with their adjusting these two pipelines -- estimated to cost $259,600 and;
WHEREAS, Mobil will require $259,600 be escrowed with them prior to any
pipeline adjustments being started;
BE IT RESOLVED BY the City Council of the City of North Richland Hills, Texas
that:
The City of North Richland Hills will reimburse Mobil Pipe Line Company for the
total actual cost of the adjustment of the 8-inch and 16-inch pipelines across the Calloway
Branch channel between Maplewood Avenue and Lola Drive. An amount of $259,600 will
be paid Mobil as escrow for the proposed pipeline adjustments. After completion of the
pipeline adjustments, a detailed breakdown of the cost will be sent the City with
reimbursement for any amount remaining from the escrow or an invoice for the additional
costs over the $259,600 escrow.
PASSED AND APPROVED this 13th day of July, 1992.